WESTFIELD PARK PRIMARY SCHOOL
PARENT & CHILD CENTRE
Client WA DEPT OF EDUCATION / BMW
Project Westfield Park PS Parent & Child Centre
Value $870,740.00 incl GST
Timeline 22 weeks (2 weeks early)
Completion Aug 2019
Architect Hodge Collard Preston Architects
Summary
Rivett Construction was awarded the construction contract for the new Parent & Child Centre as part of a refurbishment of the existing 1970s facilities. The project was completed 2 weeks ahead of the construction programme.
Key Building Features
-
Refurbishment of the existing 1972 teaching block to create the new Parent & Child Centre.
-
Extensive landscaping and certified Nature Play areas.
Key Challenges
-
Building within an operational school environment
-
After-hours shutdown & changeovers to ensure continued amenity for the client; Limited site access;
-
Tight construction programme.
-
ACM material removal and rectification.