St Columbas
Primary School
Stage 7
Client Catholic Education WA
Project St Columbas CPS Stage 7
Value $4,154,534.00
Timeline 44 weeks (4 weeks early)
Completion March 2017
Architect Parry & Rosenthal Architects
Project Summary
Rivett Construction was awarded the construction contract for the new Administration, Undercover Hardcourts & the refurbishment of the existing Heritage Church building. The extensive refurbishment of the existing 90 year old parish building to provide a modern teaching and meeting space was a project highlight. Rivett was able to complete this $3.6m project within the functioning school environment with minimal effect on the school operations.
Key Building Features
-
480sqm Administration Building & Staff facilities;
-
627sqm Undercover sporting courts and assembly area;
-
Refurbishment & restoration of 90 year old church to create new teaching and meeting spaces.
-
Management & Removal of ACM contaminated soils and building materials.
Key Challenges
-
Superior Stand of finish to reflect the original building and previous construction stages;
-
Building within an operational school environment;
-
After-hours shutdown & changeovers to ensure
-
amenity for the client;
-
Tight construction programme.
Head Office
18/127 Herdsman Pde Wembley WA 6014
PO Box 1223 Innaloo WA 6918
Contact
Email: info@rivettcs.com.au
Phone: +61 8 9387 2945
© 2020 by Rivett Construction.