Kalamunda Primary School
Administration
Client
Department of Education / Finance
Project
Kalamunda PS Additions & Alterations
Value
$1,159,847
Area
520sqm
Timeline
24 weeks (2 weeks early)
Architect
Christou Design Group
Summary
Rivett Construction was awarded the construction contract for the new Administration Building extensions as part of a refurbishment of the existing 1960s facilities. The project was completed 2 weeks ahead of the construction programme.
Key Building Features
-
324sqm Administration building & Staff facilities;
-
Separable Portions (Initial works completed in 3 weeks for new school year January 2020.
-
New carpark and civil works;
-
ACM materials both documented and undocumented​
Key Challenges
-
Building within an operational school environment
-
After-hours shutdown & changeovers to ensure continued amenity for the client; Limited site access;
-
Tight construction programme;
-
Limited site access.