Kalamunda Primary School
Administration

Client               

Department of Education / Finance

Project

Kalamunda PS Additions & Alterations

Value

$1,159,847

Area

520sqm

Timeline

24 weeks (2 weeks early)

Architect

Christou Design Group

Summary

Rivett Construction was awarded the construction contract for the new Administration Building extensions as part of a refurbishment of the existing 1960s facilities. The project was completed 2 weeks ahead of the construction programme.

Key Building Features
  • 324sqm Administration building & Staff facilities;

  • Separable Portions (Initial works completed in 3 weeks for new school year January 2020.

  • New carpark and civil works;

  • ACM materials both documented and undocumented​

Key Challenges 
  • Building within an operational school environment

  • After-hours shutdown & changeovers to ensure continued amenity for the client; Limited site access;

  • Tight construction programme;

  • Limited site access.