![RCS_KPS_20200605_011 [Deprimo Photography]_edited.jpg](https://static.wixstatic.com/media/10a134_97ad6af38e7e4ee19a353faa6ac42881~mv2.jpg/v1/fill/w_960,h_640,al_c,q_85,enc_avif,quality_auto/10a134_97ad6af38e7e4ee19a353faa6ac42881~mv2.jpg)
Salvado Catholic College
Client
Salvado Catholic College / CEWA
Project(s)
Stage 4 - Administration
Stage 5 - GPLA, Civil Works, Landscaping (Ovals)
Value
3.5m + 8.2m
Area
8,500sqm
Timeline
36 weeks, 46 weeks
Architect
Paterson Architects
Summary
Rivett Construction was awarded the construction contract for the new Administration Building extension to expand the operations of the growing college. In addition Rivett have continued the strong relationship with Stage 5, being an additional 1900sqm GPLA and substantial ovals and civil works.
​
Following the completion of this work, Rivett have been awarded Stages' 6 and 7 for completion by May 2026.
​
Key Building Features
-
424sqm Administration building & Staff facilities;
-
1900sqm GPLA teaching block
-
12,000sqm oval and playing fields.
-
New carpark and civil works;
Key Challenges
-
Building within an operational school environment
-
After-hours shutdown & changeovers to ensure continued amenity for the client; Limited site access;
-
Tight construction programme;
-
Limited site access.