Salvado Catholic College Stages' 6&7

Client               

Catholic Education WA Inc

Project

Salvado Catholic College, Abernethy Rd Byford WA.

Value

 Stage 6 - $9,187,770.00

 Stage 7 - $5,981,389.00

Area

1350sqm + 940sqm

Timeline

76 weeks (75 weeks completed) 2023-2026

Architect

Paterson Architects 

Project Summary

Rivett Construction were award four consecutive stages at Salvado Catholic College Byford maintaining a consistent team and sold relationship with the College and design team. The final two projects have expanded the school capacity and facilities towards being the premier K-12 school in the region.

 

Key Project features

  • 13,500sqm oval and sport facilities.

  • 2 off teaching blocks with an addition 2290sqm of teaching space and staff/student areas (16off GPLAs).

  • Specialised teaching block for Catering and Hospitality training.

  • Alterations buildings  to create additional VET teaching spaces.

  • Extensive landscaping and civil works.

  • High quality finishes

  • New Courtyard areas.

  • New carpark and civil works.

Key Challenges

  • Building within an operational school environment;

  • After-hours shutdown & changeovers to ensure continued amenity for the client;

  • Limited site access;

  • Tight construction programme.

  • High Water table and difficult soil conditions and civils.