Salvado Catholic College Stages' 6&7
Client
Catholic Education WA Inc
Project
Salvado Catholic College, Abernethy Rd Byford WA.
Value
Stage 6 - $9,187,770.00
Stage 7 - $5,981,389.00
Area
1350sqm + 940sqm
Timeline
76 weeks (75 weeks completed) 2023-2026
Architect
Paterson Architects
Project Summary
Rivett Construction were award four consecutive stages at Salvado Catholic College Byford maintaining a consistent team and sold relationship with the College and design team. The final two projects have expanded the school capacity and facilities towards being the premier K-12 school in the region.
Key Project features
-
13,500sqm oval and sport facilities.
-
2 off teaching blocks with an addition 2290sqm of teaching space and staff/student areas (16off GPLAs).
-
Specialised teaching block for Catering and Hospitality training.
-
Alterations buildings to create additional VET teaching spaces.
-
Extensive landscaping and civil works.
-
High quality finishes
-
New Courtyard areas.
-
New carpark and civil works.
Key Challenges
-
Building within an operational school environment;
-
After-hours shutdown & changeovers to ensure continued amenity for the client;
-
Limited site access;
-
Tight construction programme.
-
High Water table and difficult soil conditions and civils.